Area dell'identificazione
Codice di riferimento
JM-AIY/OttomanRegisters/Vol4/p20a/item137
Titolo
Court case against former contractors for construction of slaughterhouse, 10 September 1895 (Gregorian calendar) - 29 Agustos 1311 (Ottoman fiscal calendar (Rumi)
Date
- 1895-09-10 (Creazione)
Livello di descrizione
Unità documentaria
Consistenza e supporto
1 item
Area del contesto
Nome del soggetto produttore
(Early 1860s)
Istituto conservatore
Storia archivistica
Modalità di acquisizione
Area del contenuto e della struttura
Ambito e contenuto
Since the new slaughterhouse has been established, and in accordance with the information of the court of first instance, it has been decided by the council to bring suit against the contractor Yûsuf Jiryis Abû-Dayyah in order to obtain a judgment of the amount spent by proxy in addition to review all lawsuits of the council. In order to pay the needed fees for the above-mentioned lawsuit at the court of first instance, this decision was taken on the 29th of Agustos (1)311 (10th of September 1895).
[7 signatures]
Valutazione e scarto
Incrementi
Sistema di ordinamento
Area delle condizioni di accesso e uso
Condizioni di accesso
Condizioni di riproduzione
Lingua dei materiali
arabo